SunZia, a massive clean energy project in the US Southwest, has closed $11 billion non-recourse financing and launched full construction.
Daniel Elkort, executive vice president at Pattern Energy, the project’s California-based developer, said about the milestone finance package:
The size and scale of both the SunZia project and this multifaceted financing show that the renewable energy space can secure attractive capital at levels previously only seen in traditional generation.
The largest clean energy project in the US comprises two arms: SunZia Wind and SunZia Transmission. The projects will employ more than 2,000 workers onsite during construction, including heavy equipment operators, electricians, laborers, and others.
SunZia Wind is the largest wind project in the Western Hemisphere. The 3,500-megawatt (MW) wind farm is being built across New Mexico’s counties of Torrance, Lincoln, and San Miguel.
SunZia Transmission is a 550-mile ± 525 kV high-voltage direct current (HVDC) transmission line between central New Mexico and south-central Arizona. When complete, it will have the capacity to transport 3,000 MW of clean energy.
SunZia Transmission will enable SunZia Wind to supply customers in Arizona and California during early evening hours when demand is high but available renewable energy supply is low. It’s going to use the same corridor as the Western Spirit Transmission Line:
Wind turbine giant Vestas announced yesterday that it’s secured a firm order from Pattern Energy Group to supply 242 V163-4.5 MW turbines for SunZia Wind.
The 1.1-gigawatt (GW) order is Vestas’ largest order to date in the US market and its largest single onshore project globally. It’s also the largest order globally for Vestas’ newest high-capacity factor turbine.
Turbine delivery is expected to begin in the first quarter of 2025, with final commissioning scheduled for the first half of 2026.
Top comment by Martin
What's amazing to me is the speed of deployment:
Turbine delivery is expected to begin in the first quarter of 2025, with final commissioning scheduled for the first half of 2026.
I love my nuclear power, but it's hard to compete with a full build out taking only 2 years and change.
Read more: In Montana, wind is about to overtake coal generation capacity
Photo: Pattern Energy
To limit power outages and make your home more resilient, consider going solar with a battery storage system. In order to find a trusted, reliable solar installer near you that offers competitive pricing, check out EnergySage, a free service that makes it easy for you to go solar. They have hundreds of pre-vetted solar installers competing for your business, ensuring you get high quality solutions and save 20-30% compared to going it alone. Plus, it’s free to use and you won’t get sales calls until you select an installer and you share your phone number with them.
Your personalized solar quotes are easy to compare online and you’ll get access to unbiased Energy Advisers to help you every step of the way. Get started here. – ad*
FTC: We use income earning auto affiliate links. More.
Comments